某电厂吸收塔出口烟道钢支架变形原因分析与加固方法

Deformation reason analysis and reinforcement measures of outlet flue duct steel bracket of an electric plant absorbing tower
下载PDF
导出
摘要 对某电厂吸收塔出口烟道钢支架结构出现过大变形事故的原因进行了分析,认为其主要原因是结构施工过程与设计计算模型的差异以及构件较大的初始安装变形,导致了结构受载后的过大变形。根据实际施工过程计算钢支架各支座承担的荷载,并对变形后的结构进行了分析及加固验算,对不满足安全使用要求的构件进行了加固,以使该结构能够满足正常使用要求。 The oversize deformation mason of outlet flue duct steel bracket structure of an electric plant absorbing tower is analyzed. The difference between the structure construction process and numerical model and rather large original erection deformation of structure members lead to the oversize deformation after the structure bear loads. The loads the steel bracket supports bear are calculated according to the actual construction process, and the deformed structure is analyzed and calculated. Those members that aren't satisfied with safe use requirements are reinforced to make this structure satisfy normal application requirements.
出处 《四川建筑科学研究》 北大核心 2008年第5期74-77,共4页 Sichuan Building Science
关键词 过大变形 施工过程 加固方法 应力比 oversize deformation construction process reinforcement measures stress ratio
  • 相关文献

参考文献4

  • 1.GB50017-2003钢结构设计规范[S].北京:中国计划出版社,2003..
  • 2GB5009-2001建筑结构荷载规范[S].北京:中国建筑工业出版社,2002.
  • 3GB50011-2001,建筑抗震设计规范[S].北京:中国建筑工业出版社.2002.
  • 4GB50205-2001钢结构工程施工质量验收规范[S].北京:中国建筑工业出版社,2002.

共引文献742

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部