深圳市南山水厂一期工程工艺设计与自控要点 被引量:4

Design and automatic control on the first phase of Nanshan Water Supply Plant project in Shenzhen City
下载PDF
导出
摘要 深圳市南山水厂一期工程规模20万m3/d,为保证供水水质达到直接饮用目标,采用预处理—强化常规处理—臭氧活性炭深度处理工艺,并对排泥水进行回用和污泥处置。阐述了水厂工艺主要构筑物设计参数和自控条件,并对其中药剂品种与投加点、滤池恒水位过滤与初滤水排放、活性炭滤池增设砂垫层、污泥浓缩池排泥控制等一些关键技术进行说明。 The capacity of the first phase of Shenzhen Nanshan Water Supply plant project is 200 000 m^3/d. In this project, a combined technique consisting of pretreatment, enhanced conventional processing and advanced treatment is performed so as to meet the drinking water standard. This combined process includes the reuse of the sludge effluent and the treatment of the sludge. This article discusses the design parameters of the major structures and the corresponding automatic control points. It also demonstrates the key technologies concerning the addition species and the locations, filtering with constant water level and discharge of initial effluent, adding sand cushion in carbon filter and the control of sludge discharge in sludge thickening tank.
出处 《给水排水》 CSCD 北大核心 2008年第10期23-27,共5页 Water & Wastewater Engineering
关键词 预处理 强化常规处理 深度处理 污泥处理 工艺参数 自动控制 Pretreatment, Enhanced conventional processing Advanced treatment Sludge treatment Process parameters Automatic control
  • 相关文献

同被引文献31

引证文献4

二级引证文献15

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部