摘要
根据电站及供电地区的具体情况论述了澄江红石岩电站汛限水位、引水道断面尺寸及机组参数选择的特点;研究了调整利润比例降低还贷电价的可行性。
According to thd concerte conditions of power station and power supply area, the limit water level at Hongshiyan Hydropower Station,Chengjiang County during flood seasons, as well as the profile of diversion channel and features of unit parameter selection are stated in this paper. The feasibilty of profit rate regulation and reducing the repayment debt of power rate are studied also.
出处
《云南水力发电》
1997年第2期19-22,共4页
Yunnan Water Power
关键词
汛期限制水位
水能参数
水电站设计
动能经济
Hongshiyan Hydropower Station, limit water level during flood seasons, hydroenergy parameter, repayment debt of power rate