摘要 小湾拱坝高292m,坝址河谷宽、岸坡相对较平缓,拱圈又比较扁平,应进行沿建基面的抗滑稳定复核计算。本文介绍了复核计算的基本概念及算式,并列举了计算成果。 Xiaowan Arch Dam will be 292 m in beight. The river bed is wide at the damsite. Otherwise, bank slopes are relatively mild and the arch ring is rather flat. Therefore, a re-check calculation of stability against sliding along the foundation base is carried out. This paper deals with the basic conception and formulae in the re-check calculation, and the results of this calculation are cited as well.
出处 《云南水力发电》 1997年第2期65-68,38,共5页 Yunnan Water Power
关键词 拱坝 建基面 抗滑 安全系数 稳定分析 混凝土坝 foundation base of arch dam, stability against sliding, safety factor