摘要
阐述了早时标网络计划的编制特点,结合多年的教学和实践,总结出早时标网络计划的绘制方法和步骤,通过实例证明,早时标网络计划具有图形表达直观、逻辑关系明确等优点。
The author describes the compilation characteristics of the early time scale network planning, summarizes the drawing method and the steps of the early time scale network planning combined with the teaching and practice for many years, the practice shows that the early time scale network planning has the advantages such as the figure intuition and the clear logical relation and so on.
出处
《山西建筑》
2008年第30期230-231,共2页
Shanxi Architecture
关键词
早时标网络计划
施工组织设计
最早时间
early time scale network planning, construction organization design, the earliest date