摘要 结合工程实例,介绍了灰土夯扩桩在高层住宅楼湿陷性黄土地基处理中的应用。从地基的湿陷性消除、复合地基的承载力等方面进行了试验与分析,认为在大厚度湿陷性黄土地基上的高层建筑,采用灰土夯扩桩处理地基经济可行。 Based on the engineering practice, in this paper, the application of the lime - soil rammed piles in the high -rise residential buildings is introduced. By testing and analyzing the removal of the collapsibility and the bearing capacity of the composite foundation, it is thought that on the very thick wet -collapsible loess foundation, adopting the lime -soil tamping piles to build the high- rises is economical and feasible.
作者 马晓蓉
出处 《建材技术与应用》 2008年第10期20-22,共3页 Research and Application of Building Materials
关键词 湿陷性黄土 地基处理 灰土桩 复合地基承载力 wet, collapsible loess foundation treatment rammed- expanded lime soil pile bearing capacity of the composite foundation
  • 相关文献

参考文献1

  • 1[3]GB 50025-2004,湿陷性黄土地区建筑规范[S].

共引文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部