从天花板水电站工程截流时段、截流流量选择及截流施工规划等进行截流施工设计,通过截流施工的实施,说明该施工设计方案是合理的。在截流中,采取一定的工程技术和管理措施降低了截流难度。
The construction practice of river closure has proved that the design of the river closure is successful in terms of selection of duration and discharge for river closure as well as construction planning for fiver closure for construction of Tianhuaban hydropower project on the Niulanjiang river. Certain technical and managerial measures were taken to lessen the difficulty in the river closure during river closure.
出处
《云南水力发电》
2008年第5期87-89,102,共4页
Yunnan Water Power
关键词
牛栏江
水电站
截流
施工设计
戗堤
the Niulanjiang River
hydropower project
river closure
construction design
berm