摘要
介绍了塑料排水板和高压旋喷桩处理桥头路基的加固原理、设计方案和沉降观测成果,重点分析了两种处理方案达到的沉降速率、工后沉降、固结度等,结论表明预压期和预压荷载对于桥头地基处理效果至关重要。
This paper introduces the strengthening principle, design scheme and settlement observation achievement of the treatment of bridgehead roadbed. Moreover, this paper emphatically analyzes the settlement rate, settlement after construction and degree of consolidation that these two schemes can achieve. The conclusion shows that the pre-compression term and pre-load is very important for the foundation treatments effects.
出处
《山西建筑》
2008年第32期276-277,共2页
Shanxi Architecture
关键词
高压旋喷桩
塑料排水板
预压期
沉降观测
固结度
high-pressure jet grouting pile, plastic drainage plate, pre-compression term, settlement observation, degree of consolidation