摘要
论述了新湖大桥的工程概况,分析了新湖大桥水中灌注桩的工程特点,深入探讨了该主桥水中灌注桩的施工测量控制及施工过程控制,提出了该工程环保施工的具体措施,得出了该工程施工效果良好的结论。
It discusses the engineering survey of Xinhu Bridge, analyzes engineering characteristics of pouring pole in water of Xinhu Bridge, thoroughly discusses constructing test control and constructing process control of pouring pole in water of this main bridge, puts forward concrete measures of this engineering environmental protection construction, reaches a good conclusion of this project constructing effect.
出处
《山西建筑》
2008年第32期327-329,共3页
Shanxi Architecture
关键词
钻孔灌注桩
群桩基础
测量
施工控制
drilling pouring pole, group pole foundation, test, constructing control