期刊文献+

压力隧洞充水运行过程的数值模拟分析研究 被引量:5

THE NUMERICAL SIMULATION ANALYSIS OF WORKING PROCESS FOR PRESSURE TUNNEL FILLED WITH WATER
下载PDF
导出
摘要 在压力隧洞充水运行时,对衬砌与围岩之间的接缝采用接缝空腔单元模拟。运用荷载分级、变刚度迭代的三维弹塑性有限元法合理地模拟衬砌与围岩的接触过程。根据接触过程中衬砌塑性区、应力场和位移场的变化规律,在其可能开裂部位通过设置预裂单元模拟衬砌开裂后其切向应力的释放、转移过程。最后通过一工程实例计算得出一些有实际工程参考价值的结论。 The process of contact development of lining and rock mass is correctly simulated, after pressure tunnel is filled with water. The slot elements are set up to simulate slot between lining and rock mass and the 3 D elastoplastic FEM is adopted with multi stage load and changible stiffness iteration. According to the variation laws of plastic zone, stress and displacement fields of concrete lining in the contact process, the transfering process of tangential stress of lining and rock mass can be well simulated by setting up precrack element at possible crack position. Finally, some useful conclusions are presented by calculating an actual tunnel project through above method .
出处 《岩石力学与工程学报》 EI CAS CSCD 北大核心 1997年第5期453-460,共8页 Chinese Journal of Rock Mechanics and Engineering
关键词 压力隧洞 水工隧洞 充水运行 接缝 衬切 模拟 pressure tunnel, slot element, contact process, contact angle, precrack element
  • 相关文献

参考文献5

  • 1潘家铮,水工压力隧洞和调压室.水工压力隧洞部分,1992年
  • 2周维垣,高等岩石力学,1990年
  • 3汪胡桢,水工隧洞的设计理论和计算(第2版),1990年
  • 4Hsien S S,Comput Struct,1988年,28卷,3期,373页
  • 5俞裕泰,岩石力学与工程学报,1987年,6卷,1期,47页

同被引文献61

引证文献5

二级引证文献20