预应力混凝土连续梁桥悬浇施工控制技术 被引量:2

Cantilever Construction Control of the Continuous Prestressed Beam
下载PDF
导出
摘要 预应力混凝土连续梁桥采用挂篮现浇悬臂施工,施工技术要求高,为使得该桥顺利合拢,符合设计要求,对该桥进行施工控制。通过现场施工控制,该桥中跨合拢时的合拢段两端实测高程差与施工控制预计高程差在监控要求的范围内,应力也在设计要求的范围内,说明该桥的施工控制是成功的,从而为工程施工提供一种有效施工控制技术。 The continuous prestressed beam was constructed with cantilever construction, this construction was high of technology, so the bridge was supervised and controlled in the whole construction. The high- ness difference of theory and practice is accord with the code, the cantilever construction of the continuous box girder is succeeded in construction control. This refers to the construction of this sort bridges.
出处 《交通科技与经济》 2008年第6期40-41,共2页 Technology & Economy in Areas of Communications
关键词 连续箱梁 现浇悬臂施工 施工控制 continuous box girder cantilever construction construction control
  • 相关文献

参考文献3

  • 1邵旭东.桥梁工程[M]人民交通出版社,2004.
  • 2黄绳武.桥梁施工及组织管理[M]人民交通出版社,1999.
  • 3姚玲森.桥梁工程[M]人民交通出版社,1985.

同被引文献10

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部