宝泉抽水蓄能电站地下工程及下水库工程监理

Supervision on the Underground Project and Lower Reservoir of Baoquan Pumped Storage Power Station
下载PDF
导出
摘要 在宝泉抽水蓄能电站工程施工过程中,中国水利水电建设工程咨询北京公司河南宝泉监理部始终以合同为依据,以安全为前提,以质量为中心,以进度为主线,以投资为重点,以"安全环保、达标投产、争创国优"的建设目标为监理原则,狠抓各项规章制度的建设和落实,使工程建设始终处于受控状态。 In the construction of the Baoquan Pumped Storage Power Station, the Henan Baoquan Supervision Division of the Beijing Company of China Water Resources & Hydropower Engineering Consulting Corporation always insisted on the contract as its basis, the safe as its premise, the quality as its center, the progress as its main line, the investment as its focus point, and the construction goal of "safety and environmental protection, goal realization and power generation, striving for the achievement of state-level excellent project" as its supervision principle, and strictly formulated and implemented the various rules and regulations, and carrying out each item the rules and regulations, in order to make the construction of project always under control.
作者 张浩臣
出处 《水力发电》 北大核心 2008年第10期51-53,共3页 Water Power
关键词 工程监理 安全控制 质量控制 进度控制 投资控制 争创国优 宝泉抽水蓄能电站 project supervision safety control quality control progress control investment control striving for the achievement of state-level excellent project Baoquan Pumped Storage Power Station
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部