主要结合新胜高速公路后张法预应力混凝土T形梁的施工,介绍了后张法预应力混凝土T形梁的施工工艺、施工方法、主要施工设备,以及施工中可能出现的主要问题的处理措施和注意事项。
Combined with construction of post-tensioned prestressed concrete T-typed beam in Xin-Sheng express highway, the construction technology, method and principle construction equipment of post-tensioned prestressed concrete T-typed beam, tie treating measures of problems maybe occurred and matters need attention were introduced.
出处
《山西建筑》
2008年第34期151-152,共2页
Shanxi Architecture
关键词
后张法
预应力混凝土T形梁
施工工艺
施工设备
注意事项