摘要
阐述了厦门海底隧道衬砌高性能混凝土配合比方案的设计技术路线。重点分析了高性能混凝土配合比方案在应用过程中需要注意的环节。通过现场试验验证,最终确定应用于工程中的施工配合比。
The design technology-way of high-performance concrete mix-ratio projects used in second-level lining of Xiamen-xiang'an undersea tunnel engineering is discussed.The several facets be regarded of high-performance concrete mix-ratio projects used in the engineering are emphatically analyzed.Based on the practically testing,the practicall concrete mix-ratio used in the engineering is confirmed finally.
出处
《混凝土》
CAS
CSCD
北大核心
2008年第11期83-88,共6页
Concrete
关键词
海底隧道
衬砌高性能混凝土
配合比方案
设计技术路线
现场试验验证
施工配合比
undersea tunnel
high-performance concrete used in second-level lining
mix-ratio projects
the design technology-way
the practi- cal testing
the practical concrete mix-ratio