介绍了一次调频的基本原理及测试方法,并结合龚嘴水电站3号机组进行一次调频性能测试与分析,对机组的一次调频性能进行了全面评价,提出了相关的运行改进意见。
Basic principles and testing method of primary frequency modulation are described.According to performance testing and analysis on primary frequency modulation for the No.3 unit at Gongzui hydropower station,a comprehensive assessment on the unit was performed and corresponding operation improvements are proposed.