摘要
南堡35-2项目CEP平台,单片预制组装达千吨,平台总质量达5千多吨,文章以该平台为例,根据相关规范标准以及多年积累的施工经验,分析了千吨级以上大型平台陆地组片的防变形控制问题,提出了具体的预防措施。
In the CEP platform construction of Nanpu 35-2 Project,single prefabricated module weighs one thousand tons and the total platform weight is more than five thousand tons.Taking this platform as an ex-ample,and based on relevant codes and standards as well as many years' construction experience,this paper analyzes deformation control of prefabricating piece-assembled modules of large scale platforms with the weight over one thousand tons in land,and brings forward some concrete preventive measures.
出处
《石油工程建设》
2008年第6期35-37,共3页
Petroleum Engineering Construction
关键词
大型海上平台
预制
组片
防变形措施
large scale offshore platform
prefabrication
piece-assembly
anti-deformation measure