摘要
介绍了上海500 kV世博地下变电站的变电规模和电气主接线情况、电气总平面布置及设备选型、主变第3绕组电气的确定计算机监控系统、结构、通风,冷却水系统及主变压器及高抗消防等方面的内容。
The construction scale, the main electrical wiring, the electrical layout, and equipment type election of the 500 kV underground Shibo Substation are presented, as well as determination of the third winding voltage of the main transformer, the service system, the computer monitoring system, and the fire prevention for the main transformer and the high voltage reactor.
出处
《华东电力》
北大核心
2008年第11期55-58,共4页
East China Electric Power