摘要
在渤海自安装采油平台中首次采用了蒸汽锅炉+汽轮机的电站方案。蒸汽动力方案对于充分利用伴生气、减少原油燃料消耗、实现节能减排具有重要意义。在此方案中采用了2台产量为20t/h的蒸汽锅炉。为满足锅炉给水的要求,给水除盐处理过程采用了真空闪蒸海水淡化+EDI电除盐水处理+化学加药处理,实现了给锅炉提供合格给水的功能。并以渤海自安装采油平台为例,介绍了部分相关工艺。
The power system which consists of steam boiler and steam turbine is used on Bohai Bay firstly. The plan has important value in using associated gas sufficiently and reducing pollutant. In the plan two steam boilers are used which produce 20t steam per hour. For meeting the requirement of boiler water, the sea water will be treated by means of vacuum flash distillation electrical desalt and chemical injection. In this article, the description about the process of water supply treating system for boiler is given.
出处
《中国造船》
EI
CSCD
北大核心
2008年第A02期218-223,共6页
Shipbuilding of China