煤液化装置减压塔抽真空系统的优化设计 被引量:1

Optimization Design for Equipment of Vacuum Tower in Coal Liquefied Plant
下载PDF
导出
摘要 针对基础设计阶段煤液化装置减压塔抽真空系统循环水消耗量大的问题,结合装置所在地区的气候条件,按照循环水冷却改为空气冷却的思路,提出了优化设计方案。与基础设计方案相比,采用优化方案可以节省循环水1904.35 t/h,节约标油888 t/a,装置年操作费用降低324.45万元,综合效益显著。 The optimization design method, to solve the problem of the vast water consumed in vacuum process of decompression tower in the coal liquefied plant, was put forward according to the weather condition and idea of the water-cooling replaced to air-cooling. The optimization design method has been used in the plant, the air-cooling compared with water-cooling, the circulating water of 1 904.35 t/h, standard fuel oil of 888 t/a, and operation cost of RMB 3.244 5 million/a saved.
作者 马振忠
出处 《石化技术》 CAS 2008年第4期33-36,共4页 Petrochemical Industry Technology
关键词 减压塔 抽真空系统 优化设计 vacuum tower, vacuum process, optimization design
  • 相关文献

参考文献2

  • 1陈瑞斌.神华“煤制油”-工业化生产近在咫尺.中国神华煤制油,2007,(5):48-48.
  • 2国家经济贸易委员会.SH/T 3110-2001石油化工设计能量消耗计算方法[S].北京:中国石化出版社,2002.

同被引文献1

引证文献1

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部