摘要
以京沪线黄河涯站、三唐站更换GLC(06)01型提速道岔为例,从前期道岔测量定位、道岔预铺、要点施工慢行前、慢行中、封锁后等施工工序,详细介绍了更换提速道岔的施工技术,为相关工程实践提供借鉴与帮助。
Taking the example of changing the original rail track of Huangheya stop and Santang stop of Beijing-Shanghai railway into GLC (06)01 speed-raising turnout, it elaborates the construction technology of speed-raising turnout replacing from the first-phase turnout surveying and positioning, turnout pre-paving, construction procedures of key construction before low-speed running, in low-speed running, and after sealing, and elaborates the construction technology of speed-raising turnout replacing, which provides a reference for relevant projects.
出处
《山西建筑》
2009年第1期303-304,共2页
Shanxi Architecture
关键词
既有线
提速道岔
施工技术
original rail track, speed-raising turnout, construction technology