摘要
本文从宽厚板轧机装备水平的进步、企业生产能力和上下工序匹配及开发新产品、积极抢占高端市场的需要出发,综合论述了易地改造4200mm轧机、建设5000mm宽厚板生产线的必要性和可行性。
The article comprehensively elaborates the necessity and the feasibility of constructing 5 000 mm wide and heavy plate mill production line for relocated modification of 4 200 mm plate mill based on the demands of equipment level advancement of wide and heavy plate mill , the production capacity of the enterprise, the matching of upstream and downstream production procedures, new product development, high end market occupation.
出处
《宽厚板》
2008年第6期1-4,共4页
Wide and Heavy Plate
关键词
宽厚板
易地改造
5000mm轧机
Wide and heavy plate, Relocated modification, 5 000 mm plate mill