摘要
介绍了新建武广铁路客运专线SDⅢ标大瑶山2号隧道Ⅲ级,Ⅳ级围岩光面爆破的适用范围条件、材料要求、施工工艺、施工质量控制要点及施工注意问题,积累了围岩光面爆破施工经验。
The paper introduces the utility scopes, material requirements, the construction craft, key points of quality control and matters needing attention for construction of the Ⅲ -class and Ⅳ-class surrounding rock in the No. 2 tunnel of SDⅢ Dayaoshan along the newly-built Wuhan-Guangzhou special railway and accumulates experience for the smooth blasting construction of the surrounding rocks.
出处
《山西建筑》
2009年第2期320-321,共2页
Shanxi Architecture
关键词
石灰岩地区
隧道
围岩
光面爆破
施工工艺
karst region, tunnel, surrounding rock, smooth blasting, construction craft