摘要
本文针对复式交分道岔转换设备中双转辙器部分杆件多、安装烦琐、调试复杂的特点,结合工程施工经验,详细介绍了安装与调试的方法。
With the experience of project construction, this article describes the method of installation and debugging of two-point machines with the characteristics of so many member bars, cumbersome installation, and complex debugging in the conversion equipment of double slip switches.
出处
《铁路通信信号工程技术》
2008年第6期59-61,共3页
Railway Signalling & Communication Engineering
关键词
复式交分道岔
转换设备
安装
调试
Double slip switches, Conversion equipment, Installation, and Debugging