摘要
利用恶滩电站老机组原有厂房进行了增容改造。改造机组的上游正常水位抬高后,使过流部件承受压力增大。对改造机组的顶盖进行了受力分析,以确定改造机组是否需要更换新的顶盖。
The old unit of Etan Hydropower Station was reformed for capacity expansion using the original power house. The normal level in upper reaches of reformed unit was raised, and the pressure upon the flow components was increased. The force analysis of upper cover of reformed unit was accomplished, and it is determined by which that whether require to replace a new upper cover for the reformed unit.
出处
《华电技术》
CAS
2009年第1期14-16,共3页
HUADIAN TECHNOLOGY
关键词
电站增容改造
机组参数
顶盖
受力分析
计算
reformation for capacity expansion of hydropower station
parameters of unit
upper cover
force analysis
calculation