摘要 讨论了生产时间可变的多产品间歇过程的最优调度问题,给出了间歇过程在复杂中间的无限存储策略、有限存储策略、无中间存储策略和混杂存储策略下p-时间Petri网模型的描述方法,进而给出了基于可行调度集和修正分枝界定的间歇过程最短生产时间的最优调度算法。该算法利用一间歇过程最短生产时间不大于另一间歇过程最短生产时间的条件,有效地限制了对解空间的搜索,进而改善了算法的计算性能。仿真算例表明了所述方法的有效性。 Optimal scheduling problem of batch process with variable cycle time was discussed. A p time Petri net model description approach for batch process with complicated intermediate storage policies (such as: unlimited intermediate storage, finite intermediate storage, no intermediate storage, and mixed intermediate storage) was presented. Then, an algorithm for short term scheduling of batch process based on a feasible scheduling set and a modified branch & bound was developed. In this method, by applying the condition that the minimal makespan of one batch was not longer than the minimal makespan of the other batch, thereby the explicit enumeration of search was avoided so that the algorithm performance was improved. Effectiveness of the proposed approach and algorithm were demonstrated by simulation.
出处 《计算机集成制造系统》 EI CSCD 北大核心 2009年第1期109-116,共8页 Computer Integrated Manufacturing Systems
基金 国家自然科学基金资助项目(60563005) 广西青年科学基金资助项目(0640032)~~
关键词 离散事件系统 间歇过程 调度 PETRI网 仿真 discrete event systems batch process scheduling Petri nets simulation
  • 相关文献

参考文献10

  • 1KONDILI E, PANTELIDIES C C. A general algorithm for short-term scheduling of batch opertations-Ⅰ:MILP formulation[J]. Computers and Chemical Engineering, 1993,17(2) : 211-227.
  • 2PAPAGEORGAKI S, REKLAITIS G V. Optimal design of multipurpose batch plants Ⅰ:problem formulation[J]. Industry Engineering and Chemical Research, 1990,29(8):2054-2062.
  • 3GRAELLS M, ESPUNA A, PUIGJIANER L. Sequencing intermediate products:a practical solution for multipurpose production scheduling[J]. Computers and Chemical Engineering, 1996,20(S) :1137- 1142.
  • 4KOBAYASHI S, ONO I, YAMAMURA M. An efficient genetic algorithm for Job Shop scheduling problems [C]//Proceedings of the 6th International Conference on Genetic Algorithms. San Francisco, Cal. , USA: Morgan Kaufmann Publishers Inc. , 1995:506-511.
  • 5ADAMS J, BALAS E, ZAWACK D. The shifting bottleneck procedure for Job Shop scheduling[J]. Management Science, 1988,34(3) :391-401.
  • 6CARLIER J, PINSON E. An algorithm for solving the Job- Shop problem [J].Management Science, 1989, 35 (2): 164-176.
  • 7古天龙,蔡国永,琶里莎·巴哈里.基于赋时Petri网描述的多产品间歇过程调度研究[J].控制理论与应用,2000,17(6):933-936. 被引量:6
  • 8GU Tianlong, BAHRI P A, CAI Guoyong. Timed Petri-Net based formulation and an algorithm for the optimal scheduling of batch plants[J]. Journal of Application Mathematic and Computer Science, 2003,13(4) :527-536.
  • 9NOTT H P, LEE P. An optimal control approach for scheduling mixed batch/continuous process plants with variable cycle time[J]. Computers and Chemical Engineering, 1999,23 (7) : 907-917.
  • 10JULIA S, VALETTE R. Real time scheduling of batch systems [J]. Simulation Practice and Theory, 2000,8(5):307-319.

二级参考文献2

  • 1Jeng M D,IEEE Transon Industrial Applications,1999年,35卷,1期,196页
  • 2Zhou M C,Modeling,Simulation,and Control of Flexible Manufacturing Systems:A Petri Net Ap,1998年

共引文献5

同被引文献37

引证文献4

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部