摘要
通过对变压器自身运行的经济性、电网供电可靠性、容载比、供电灵活性、投资及节约占地等方面进行分析,论述了变电所按配置了3台或4台主变压器规划的必要性和合理性。提出110kV及以上变电所宜按3台或4台主变压器进行规划和配置,但不宜超过4台。
The necessity and rationality of the plan that 3 or 4 main transformers are disposed in the substation are expounded and proved in this paper,on the basis of analysis about economical of the transformer operated,reliability for power supply of electrical network,capacity and load ralio,power supply flexibility,investment and saving on land etc.It is put forward that 3 or 4 main transformes may be planned and disposed in the substation for 110 kV or over ,but may be not over 4 transformers.
出处
《山东电力技术》
1998年第1期59-62,共4页
Shandong Electric Power
关键词
变电所
规划
主变压器
台数
Substation Planning Main transformer Number