对沙角C电厂1号机定子铁心的事故原因及修理过程的质量控制进行了叙述和分析,同时介绍了厂家在定子通风改造方面所作的研究、实际的改造方法及效果。
This paper describes and analyses the causes of the stator core failure and also the quality control during the repair of the No 1 generator of SHA JIAO ' C ' power plant. The manufacturer' s research on the improvement of stator ventilation, the practical improving method and its effects are also introduced. .
出处
《大电机技术》
北大核心
1998年第1期10-16,共7页
Large Electric Machine and Hydraulic Turbine