属性相关的关键链计划缓冲设置方法 被引量:36

A Buffer Sizing Approach in Critical Chain Scheduling with Attributes Dependent
原文传递
导出
摘要 考虑链中包含的工序数大小、工序执行时间不确定程度和开工柔性程度三个与具体项目相关的属性,研究关键链项目计划缓冲设置。以项目计划周期和完工保证率为评价目标,通过仿真实验方法评价属性对项目计划的影响。根据仿真实验结果分析,提出缓冲设置的改进方法。算例表明与切粘法和根方差法相比改进方法可显著改善项目计划性能。 Three attributes relevant to a specific project, including the number of activities in chain, their uncertain duration and flexible start time , were introduced into critical chain project management for buffer sizing. By means of simulation, the impact of these three attributes on project scheduling in terms of two performance indicators: project duration and on time completion was evaluated. Based on analyzing the simulation experiments, a revised method for buffer sizing was proposed. The case indicates that the performance of project scheduling is significantly improved by using the revised method.
出处 《工业工程与管理》 北大核心 2009年第1期11-14,共4页 Industrial Engineering and Management
基金 总装预研基金项目(9140A04050707JW0507) 通用汽车公司研究基金项目(ND22244001-RD-07.245)
关键词 缓冲设置 关键链项目管理 项目计划 仿真 buffer sizing critical chain project management ( CCPM ) projectscheduling simulation
  • 相关文献

参考文献8

  • 1Rand G K. Critical Chain= The Theory of Constraints Applied to Project Management [J]. International Journal of Project Management, 2000,18(3) : 173-177.
  • 2Steyn H. Project Management Applications of the Theory of Constraints beyond Critical Chain Scheduling[J]. International Journal of Project Management, 2002,20( 1 ) : 5.
  • 3Steyn H. An Investigation into the Fundamentals of Critical Chain Project Scheduling [J]. Internationai Journal of Project Management, 2000,19 (6) : 363-369.
  • 4杨雪松,胡昊.基于关键链方法的多项目管理[J].工业工程与管理,2005,10(2):48-52. 被引量:63
  • 5Tukel O,Rom W, Eksioglu S. An Investigation of Buffer Sizing Techniques in Critical Chain Scheduling[J]. European Journal of Operational Research, 2006,1 7 2 (2) : 401-416.
  • 6Leach L P. Critical Chain Project Management [M]. Boston: Artech House, 2000.
  • 7Herroelen W, Leus R. On the Merits and Pitfalls of Critical Chain Scheduling[J]. Journal of Operations Management, 2001, 19(5):559-577.
  • 8刘士新,宋健海,唐加福.资源受限项目调度中缓冲区的设定方法[J].系统工程学报,2006,21(4):381-386. 被引量:70

二级参考文献24

  • 1Goldratt E M. Critical Chain [ M ]. New York: The North River Press, 1997.
  • 2Leach L P. Critical chain project management [ M]. London:Artech House Inc, 2000.
  • 3Rand G K. Critical chain: the theory of constraints applied to project management[J]. International Journal of Project Management, 2000, 18(3): 173-177.
  • 4Patrick F S. Critical Chain Scheduling and Buffer Management[ DB/OL] http ://www. focusdperformance, com, 2003 -04 -05.
  • 5Patrick F S. Critical Chain and Risk Management- Protecting Project Value from Uncertainty [ DB/OL ]. http :// www.focusdperformance, corn, 2004 - 10 - 21.
  • 6Steyn H. Project management application of the theory of constraints beyond critical chain scheduling [ J ]. International Journal of Project Management, 2002, 20: 75- 80.
  • 7Goldratt E M.Critical Chain[M].Great Barrington:The North River Press,1997.
  • 8Hagemann A G.Use of the Critical Chain Project Management Technique at NASA,Langley Research Center[C].AIAA/IEEE Digital Avionics Systems Conference-Proceedings,2001,Oct,14-18:4B11-4B110.
  • 9Rand G K.Critical chain:The theory of constraints applied to project management[J].International Journal of Project Management,2000,18:173-177.
  • 10Steyn H.An investigation into the fundamentals of critical chain project scheduling[J].International Journal of Project Management 2000,19:363-369.

共引文献120

同被引文献350

引证文献36

二级引证文献151

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部