摘要
结合渝怀铁路DK318+807.25~DK318+904.75段的工程概况,介绍了桩板墙的施工流程以及锚固桩施工、螺栓端杆件预埋、路堑开挖及挂板等路堑式桩板墙的施工要点,从而减少土石方及用地数量,确保了边坡的稳定,又便于机械分层开挖和循环生产。
Combined with engineering general situation of Yu-Huai railway from DK318 + 807.25 to DK318 + 904.75 section, the pile plank wall construction process and construction points of anchor pile, bolt end member bar embedding, cutting excavation and pile plank wall were introduced, which decreased cubic metre of earth and stone and land consumption and guaranteed side slope stability and easy to hierarchical excavate mechanically and production circulation.
出处
《山西建筑》
2009年第7期111-112,共2页
Shanxi Architecture
关键词
路堑
桩板墙
施工
锚固桩
cutting, pile plank wall, construction, anchor pile