摘要 国华三河发电有限责任公司二期工程3、4号炉的脱硫系统采用了无烟气旁路、无GGH、引风机和增压风机合并、"烟塔合一"的新技术,其调试工作在国内为首次。通过探索和实践,总结出了一套有效的运行控制方式。 Desulphurization system of the second phase project in Guohua Sanhe Power Generation Co. Ltd. was constructed without gas bypass system and GGH, with combination of induced draft fan with booster fan, and with unification technique on cooling tower and chimney. The commission of this desulphurization system was the first in China. Based on plenty of exploration and practice, one set of effective operation and control approaches was summarized.
出处 《华北电力技术》 CAS 2009年第2期6-10,共5页 North China Electric Power
关键词 无旁路 脱硫系统 调试 without bypass desulphurization system commission
  • 相关文献

参考文献3

  • 1于淑芹.利港电厂脱硫机组烟气旁路挡板的运行操作及试验.2007年火电厂环境保护综合治理技术研讨会,2007.
  • 2傅文玲,杨虹.无GGH-FGD运行特性分析和设计应注意的问题[J].电力设备,2006,7(8):9-11. 被引量:5
  • 3李庆,孙辉,张新亮,等.电厂脱硫系统调试过程中遇到的若干问题(EB/OL).[2007-03-17].http://www.dsdne.org.cn/html/dianchangzhichuang/dianlijishu/guolu/20070317/1618.html.