摘要
某热电厂输煤线环境复杂,周围建筑物多、距离近,厂方要求拆除时输煤线不停产、不破坏建筑物、爆碴便于清运。经过精心设计、合理施爆,达到了预期目的,为合理选择装药系数、黄土地基振动参数、飞石距离的校核提供了有益的经验。
The waterpressure blasting demolition of a coal loadingtrugh in a power plant is introduced in this paperThis blasting practice gained success by adopting meticulous design and stringent construction under complex surroundingsSome problems such as charge parameter,vibration parameter and flying stone distance are discussed
出处
《工程爆破》
1998年第2期57-59,56,共4页
Engineering Blasting