资源约束条件下工期、质量、成本综合均衡优化 被引量:11

Proportional Optimization of Time, Quality and Cost Under Resource Restriction
下载PDF
导出
摘要 工期、质量、成本称为工程项目的三大控制目标,三者相互依存,相互影响.工程项目优化控制的理想结果是同时实现合理的工期、较低的费用和较高的质量.利用多属性效用函数以及效用分解定理,建立了基于资源约束条件下的工期、质量、成本的综合均衡优化与控制模型,并引入遗传算法,对模型进行求解.通过一个应用实例,对实际施工中的工期、质量、成本综合均衡优化给出了备选方案. Time, quality and cost, with mutual influence upon one another, are the three major controlled items for project management. The best solution for a project is to achieve high quality with low cost in a proper time limit. This paper, by employing the multi-utility function and the decomposable theory of utility, has built a model for integrated optimization of time, quality and cost under resource restriction, and by using the genetic algorithm, has solved the problem for a universal model. Then, by adducing an example, the paper provides a useful scheme for the practical work over integrated optimization and controlling model. This study bears some theoretical and realistic value to project optimization.
出处 《中南林业科技大学学报》 CAS CSCD 北大核心 2008年第6期101-105,共5页 Journal of Central South University of Forestry & Technology
基金 湖南省教育厅资助专项课题基金(058033) 中南林业科技大学引进人才项目(101-0621).
关键词 项目管理 工程项目优化 综合优化 多效用函数 遗传算法 质量成本模型 project management project optimization integrated optimization multi-utility function genetic algorithm model of quality and cost
  • 相关文献

参考文献10

二级参考文献37

  • 1李爱国.多粒子群协同优化算法[J].复旦学报(自然科学版),2004,43(5):923-925. 被引量:398
  • 2吴之明.网络计划中的时间价值与风险[J].系统工程理论与实践,1994,14(5):1-5. 被引量:9
  • 3McKim R, Hegazy T, Attalla M. Project performance control in reconstruction projects[J]. Journal of Construction Engineering and Management, 2000, 126 (2): 137-141.
  • 4Rwelamila P D, et al. Total systems intervention: An integrated approach to time, cost and quality mawgement[J]. Construction Management and Economics, 1995, 13: 235-241.
  • 5Babu A J G, Suresh N. Project management with time, cost, and quality considerations[ J]. European Journal of Operational Research, 1996, 88 (2): 320-327.
  • 6Do Ba Khang, Yin Mon Myint. Time, cost and quality trade-off in project management: A case study[J]. International Journal of Project Management, 1999, 17(4): 249-256.
  • 7Shih-Wen Hsiao. Fuzzy logic based decision models for product design[J]. International Journal of Industrial Ergonomics, 1998,21: 103-116.
  • 8玄光男 程润伟.遗传算法与工程设计[M].北京:科学出版社,2000..
  • 9Hegazy T,El-Zamzamy H. Project management software that meet the challenge[J].Cost Engineering Journal,1998, 4(5):25-33.
  • 10Johnson R. Resource constrained scheduling capabilities of commercial project management software[J]. Project Management Journal, 1992, 22(4):39-43.