海港某码头大管桩裂缝调查及维护加固措施 被引量:1

Investigation for Cracks of Large Pipe Pile in Some Harbour Wharf and Their Maintenance and Strengthing Measures
下载PDF
导出
摘要 通过现场检测和室内分析,对运营10多年的某海港码头589根后张预应力大管桩的裂缝情况进行了全面调查,初步分析了裂缝的成因及影响因素,并进行了维修加固处理。处理结果均满足设计要求,达到预期效果,为码头的安全运行提供了保障。有关技术资料可供类似工程参考借鉴。 Through field test and laboratory analysis, this paper makes a complete investigation for cracks of 589 post-tensioned prestressing large pipe pile of some harbour wharf which has been operated for more than ten years, analyzes the causes of this action and influential factors, and makes maintenance and strengthing measures. The results of treatment are all meet de- sign requirements to obtain excellent results and ensure the safety operation of wharf. The related technology information may provide references for similar projects.
出处 《中国港湾建设》 北大核心 2009年第1期59-61,共3页 China Harbour Engineering
关键词 码头 大管桩 裂缝 调查检测 维修加固 wharf large pipe pile crack investigate maintenance and strenthing
  • 相关文献

参考文献8

  • 1JTJ270-98.水运工程混凝土试验规程[S].[S].,..
  • 2靳道斌.打桩应力及纵向裂缝的试验研究报告[R].南京:南京水利科学研究院,1987.
  • 3靳道斌.预应力混凝土打桩纵向裂缝的现场试验研究[R].南京:南京水利科学研究院,1987.
  • 4靳道斌,陈锦珍.箍筋间距对预应力桩打桩纵向裂缝影响的现场试验研究[R].南京:南京水利科学研究院,1981.
  • 5阮起楠,宋建军.PHC管桩裂缝浅析[J].混凝土与水泥制品,1997(1):27-29. 被引量:1
  • 6金初阳,陈中忠华.高桩码头结构病害诊断与防治研究[R].南京:南京水利科学研究院,2000.
  • 7陆锡清.浅谈大管桩裂缝的修补工艺措施[J].港工技术与管理,1997(3):22-24. 被引量:1
  • 8JTJ269-96,水运工程混凝土质量控制标准[S].

共引文献67

同被引文献7

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部