摘要
对某厂一座2 000m3炉况失常情况,分析研究了该炉炉况失常的过程、原因及对炉况处理达到正常的过程。
The process and the reasons of the furnace operation disorder for the 2 000 m^3 BF in a factory, and the treatment process for abnormal furnace conditions to return to normal were analyzed and studied.
出处
《云南冶金》
2009年第1期43-45,72,共4页
Yunnan Metallurgy
关键词
高炉
炉况失常
处理
BF (blast furnace)
furnace operation disorder
treatment