摘要
通过对引黄工程国际Ⅱ、Ⅲ标6#、7#隧洞穿越岩溶区、地下集中涌水、及膨胀岩等的特殊地质情况,TBM施工与钻爆法施工的优缺点,TBM施工机组的选择,类似工程TBM施工实例及承包商施工计划安排中存在的问题等的分析,说明国际Ⅱ、Ⅲ标施工延迟的可能性,希望承包商专家们对备选方案给予足够的考虑。
The most possibility of delay in construction of the tunnels of International Bids No.Ⅱ,No.Ⅲ is explained based upon the following analyses:a)The special geohydrological condition such as Karst area,the high ground water level area,the swelling rock area.These conditions will probably be met by the tunnels No.6 and No.7 of International Bids No.Ⅱ,No.Ⅲ.b)The advantages and disadvantages of the TBM method and the drill blast method.c)The condition for selecting of the TBM units.d)The examples of TBM Construction in similar condition.e)The problems existing in the construction schedule of the contractor.Finally it is hoped that experts in the contractor side should make a full consideration on the alternative scheme.
出处
《山西水利科技》
1998年第2期38-42,共5页
Shanxi Hydrotechnics
关键词
TBM施工
钻爆法
岩溶区
集中涌水
引黄工程
TBM Construction\ Drill and Blast Method\ Karst Area Swelling Rock\ High Ground Water Level