采用三维渗流有限单元法对雨成电站左坝肩渗流场进行数值分析,找出引起左坝肩渗流的基本原因。并阐述了防渗帷幕的不完整性对渗流的影响程度,为工程单位采取防渗措施提供可靠的依据。
Seepage feature and calculation of applying three-dimensional finite element method for Yucheng power station is described so as to find out the reason of seepage of left part of the dam.The effect of a heavy curtain with flaw to the seepage is explained.Analysis is provided for the seepage prevention.
出处
《华北水利水电学院学报》
1998年第1期12-15,共4页
North China Institute of Water Conservancy and Hydroelectric Power
基金
四川省华能宝粉河电力股份有限公司委托项目
关键词
左坝肩
渗流场
帷幕
有限元
研究
Left part of the dam\ Seepage feature\ Heavy curtain