摘要
介绍了以上海外高桥电厂3号机为试验对象的国产300MW引进型机组的全面的经济性能的试验研究情况。对影响机组供电煤耗率的主要因素进行了定量分析,试验取得了机组供电煤耗率与负荷关系的基准曲线及不同季节的曲线,提出了降低供电煤耗率的具体措施。
An overall economic performance test of No.3 300 MW unit(CE designed boiler and westinghouse designed turboganerator) in the Wai gao qiao Power Plant is described and a quantitative analysis on major factors influencing the net coal consumption rate of the unit was carried out and the standard coal consumption rate-load curve,as well as those in diffent seasons.was obtained and finally the practical measures for reducing the coal consumption rate are suggested。