运用遗传算法优化项目级现金流问题的研究 被引量:2

Study on project-level cash flow optimization using genetic algorithm approach
下载PDF
导出
摘要 针对项目级现金流的优化问题,结合传统的资源受限项目调度模型,得到一种带现金流折现的非线性规划项目调度模型,并设计启发式遗传算法对其进行优化求解。通过引入现金流分析,项目调度模型能反映企业的财务指标,更切合实际。通过设计相应的编码方式、遗传算子和调度生成策略,提出了一种改进的遗传算法并用于求解此优化问题,数值实验结果证明了该算法的正确性和高效性。 To improve the project-level cash flow management, based on some resource-constrained project scheduling problem (RCPSP) models, a nonlinear programming project scheduling model with discounted cash flow is introduced. Cash flow analysis which reflects the financial criteria of the company makes the model more practical. By designing appropriate coding scheme, genetic operators and schedule generator, the proposed genetic algorithm (GA) is effective to solve this problem. Numerical experimental results demonstrate the effectiveness of the algorithm.
出处 《计算机工程与设计》 CSCD 北大核心 2009年第5期1168-1172,共5页 Computer Engineering and Design
基金 国家自然科学基金项目(60573066) 广东省自然科学基金项目(5003346) 教育部留学回国人员科研启动基金项目(教外司留[2006]331号)。
关键词 多模式资源约束项目调度问题 现金流 净现值 遗传算法 调度生成器 multi-mode resource constrained project scheduling problem cash flow net present value genetic algorithm schedule generator
  • 相关文献

参考文献8

二级参考文献53

  • 1华罗庚.华罗庚科普著作选集[M].上海:上海教育出版社,1984..
  • 2Vanhoucke M, Demeulemeester and Herroelen. Discrete time/cost trade-offs in project scheduling with time-switch constraints[J].Journal of Operational Research Society,2002,53(7):741~751.
  • 3Tarek H. Optimization of construction time-cost trade-off analysis using genetic algorithms[J]. Canadian of Civil Engineering,1999,26(6):685~697.
  • 4De P,Dunne E J,Ghosh J B,Wells C E. The discrete time/cost trade-off problem revisited[J]. European Journal of Operational Research, 1995, 81(2):225~238.
  • 5Alcaraz J, Maroto C, Ruiz R. Solving the multi-mode resource-constrained project scheduling problem with genetic algorithms[J].Journal of Operational Research Society,2003,54(3):614~626.
  • 6Demeulemeester, E. And Herroelen, W.. A Branch - and -Bound Procedure for the Multiple Resource -constrained Project Scheduling Problem [J]. Management Science,1992,38(12): 1803 - 1818.
  • 7Bell, C. E. And Park, K.. Solving Resource - constrained Project Scheduling Problem by A* Search[J]. Naval Res.Logist. Quart. , 1990,37(1) :61 - 84.
  • 8Chiu- Chi Wei, Ping- Hung Liu and Ying- Chin Tsai.Resource- constrained Project Management Using Enhanced Theory of Constraint [J]. International Journal of Project Management,2002,20:561 - 567.
  • 9Elmaghraby, S. E.. Activity Nets; A Guided Tour through Some Resent Development[J]. European Journal of Operational Research, 1995,82:383 - 408.
  • 10Icmeli, O., Erenguc, S. S. and Zappe, C. J.. Project Scheduling Problem:A Survey[J]. International Journal of Operations and Production Management, 1993,13: 80 - 91.

共引文献19

同被引文献16

引证文献2

二级引证文献68

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部