国家对节能减排要求日益提高,火电厂流化床机组建设项目不断增多。文章介绍了南昌电厂循环流化床干法脱硫的主要设计参数及工艺流程,对运行过程中影响脱硫效率的因素进行分析并提出相应对策。
The main design variables and the technological process of Turbosorp Dry FGD in Nanchang power plant were introduced. By analyzing the factor affecting the efficiency of desulfurization in the process of operation countermeasures were put forward.
出处
《江西电力》
2009年第1期32-34,共3页
Jiangxi Electric Power
关键词
循环流化床
烟气脱硫
应用
circulating fluidized bed
flue gas desulfurization