华能玉环电厂1000MW超超临界2号机组凝汽器组合安装施工技术方案 被引量:3

Technical Installation Plan for No.2 1000 MW USC Unit Condenser of Huaneng Yuhuan Power Plant
原文传递
导出
摘要 凝汽器是发电厂重要设备之一,凝汽器的安装速度和质量直接影响着整个工程施工进度网络节点的顺利实现和今后整机的运行水平。华能玉环电厂2号机凝汽器安装施工过程中,克服了多种不利因素,制定科学便捷的施工工序和施工方案,以最短的时间完成了凝汽器的整体安装任务,为后续的酸洗和吹管,以至整套启动赢得了宝贵的时间。 As one of the key equipment of a power plant,the speed and quality of condenser installation directly' determines the schedule of whole project and future unit operation.During the process of condenser installation of Huaneng Yuhuan Power Plant's No.2 unit,rational and efficient construction procedures and plans are established after numerous unfavorable factors have been overcome.The task has been accomplished in the shortest possible time,saving precious time for following acid washing and pipe blowing,as well as entire system startup.
出处 《电力建设》 2009年第1期59-62,共4页 Electric Power Construction
基金 国家重点工程项目(发改能源[2007]1697号)
关键词 凝汽器 隔板 管板 接颈 组装 钛管 焊接 condenser diaphragm tube plate linking neck assembling titanium pipe welding
  • 相关文献

参考文献5

二级参考文献2

共引文献43

同被引文献7

引证文献3

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部