基于能力验证的模具交货期可行性分析方法 被引量:10

Approach to establish reliable due dates of mould based on capacity check
下载PDF
导出
摘要 针对模具企业在订单洽谈阶段难以确定交货期可行性这一实际问题,建立了基于能力验证方法的交货期可行性验证模型。首先在新模项目关键路径的关键工序中,构建了资源范畴这一能力验证对象,并给出了能力需求和已有负荷的计算方法,然后建立了关键负荷指数这一资源负荷评价指标。基于上述理论基础,构造了启发式算法,并通过算例说明了算法的实用性。最后,针对算法中涉及的接收概率具有不确定性的问题进行了敏感度分析。 It is difficult to establish reliable due dates of mould in customer enquiry stage. To deal with this problem, a model of due date feasibility verification was proposed based on a capacity-verification approach. Firstly, resource categories were set up as the capacity checking object from critical operations of critical path of new order project. Furthermore, the calculation approach for capacity requirement and existing workload of resource categories was provided. Secondly, the critical load index was introduced for evaluating load of resource categories. Based on above mentioned methods, a heuristic algorithm was proposed. And, practicability of this algorithm was verified by a sample calculation. A sensitivity analysis was also conducted to the uncertain parameters of receive probability involving in the algorithm.
出处 《计算机集成制造系统》 EI CSCD 北大核心 2009年第3期618-624,共7页 Computer Integrated Manufacturing Systems
基金 国家自然科学基金资助项目(50675039) 国家863/CIMS主题资助项目(2006AA04Z132) 广东省自然科学基金团队资助项目(05200197) 广东省科技攻关资助项目(2004B10201030)~~
关键词 模具 交货期 能力验证 项目模板 敏感度分析 建模 mould due date capacity check project template sensitivity analysis modeling
  • 相关文献

参考文献7

  • 1PARK C, SONG J, KIM J G, et al. Delivery date decision support system for the large scale make to order manufacturing companies[J]. Production Planning & Control, 1999, 10 (10):585-597.
  • 2KINGSMAN B G. Modelling input output workload control for dynamic capacity planning in production planning systems[J]. International Journal of Production Economics, 2000,68 (1):73-93.
  • 3CORTI D, POZZETTI A, ZORZINI M. A capacity-driven approach to establish reliable due dates in a MTO environment [J]. International Journal of Production Economics, 2006,104 (2) ,536-554.
  • 4彭杰,陈庆新,毛宁,伍岳.嵌入随机概率模型的模具项目模板及其应用[J].模具工业,2007,33(8):1-5. 被引量:8
  • 5WORDEN L, WILSON E, KINGSMAN B G, et al. Integrating marketing and production planning in make-to-order companies[J]. International Journal of Production Economies, 1993,30/31(1) :53-66.
  • 6KINGSMAN B G, MERCER A. Strike rate matrices for integrating marketing and production during the tendering process in make-to-order subcontractors [J]. International Transaction Operational Research, 1997,4(1) :251-257.
  • 7STEVENSON M, HENDRY L. Aggregate toad-oriented workload control: a review and a re-classification of a key approach[J]. International Journal of Production Economics, 2006,104(2) :676-693.

二级参考文献2

共引文献7

同被引文献73

引证文献10

二级引证文献36

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部