鞍钢某厂铸钢车间露天跨的10t吊车梁、柱通常在爆池强震条件下工作,使结构的使用寿命受到影响.介绍了在不停产的情况下,对该结构采取的几种加固方法。
The 10 t crane gither and column in the ootdoo gnn of the steel casting wordshop at a certainplant of AISC are usoally are under strong shaking condition caused by the water blasting pool. The life of thestructure is affected. Several adopted reinforcement methods of the structure without shutdown are introduced.