摘要 苏州新苏德基广场深基坑工程采用地上一层复合土钉+地下两层逆作,是该地区很有特色的工程案例。主要介绍该工程设计施工的关键技术,包括复杂周边环境、地层条件下土钉施工技术、基坑止水防水设计、土方开挖、逆作法主要施工节点处理、不均匀沉降控制等,为类似工程积累一定的工程经验。 The deep foundation pit of Xinsudeji Square in Suzhou is constructed by use of the composite soil nailing method and the top-down method.It is a very distinctive engineering case in this area.Some key design and construction techniques used in the case are mainly introduced.They include the construction technology of soil nailing in complex construction environment and stratigraphic condition,earth excavation technology,water-resistant and waterproof design,treatment of critical construction nodes and control of uneven settlement,etc.The success of this case may provide engineering experience for similar projects.
出处 《岩土工程学报》 EI CAS CSCD 北大核心 2010年第S1期420-425,共6页 Chinese Journal of Geotechnical Engineering
基金 铁道部科研重点项目(2007G045-C-1) 无锡轨道交通科研项目(GD01KYHT0901)
关键词 深基坑 自钻式土钉 逆作法 设计 施工 deep foundation pit self-boring soil nailing top-down method design construction
  • 相关文献

参考文献4

二级参考文献8

共引文献13

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部