摘要
介绍锚杆静压桩结合局部掏土用于某软土天然地基上9层住院部的加固纠偏,描述了住院部险情的发生过程、加固方案的选择以及锚杆静压桩的设计概况和施工要点,对其加固纠偏的效果进行了详细的分析,并得出了结论。
The article introduces combined application of anchor static pressure pile and local soil digging for solidification and rectification of a 9-floors inpatient building built on nature soft ground.It is described the dangerous condition of the said inpatient building,and the choice of solidification proposal for the same.It is given a brief introduction to the design and construction key points of anchor static pressure pile.The solidification effect of the said proposal is finally given in this article based on its detail analyses.
出处
《工业建筑》
CSCD
北大核心
2010年第S1期916-919,共4页
Industrial Construction
关键词
锚杆静压桩
掏土
加固纠偏
anchor static pressure pile
soil digging
solidification and rectification