在包钢矿浆管线工程中,通过实际测定各工序平均时间,计算出总工序时间和资源费用成本,分析提高效率的方法,对网络图进行优化,应用到工程实际中,效果显著。
In pulp pipeline engineering of Baotou Steel,by determining the average time spent on construction processes,the total time and cost for resource is calculated.Moreover,the method improving efficiency is analyzed and the network chart is optimized.It has been successfully applied in the actual engineering to gain good effect.
出处
《施工技术》
CAS
北大核心
2010年第S2期519-521,共3页
Construction Technology
关键词
矿浆管线
流水
网络图
优化
pulp pipeline
flow progress
network chart
optimization