摘要
介绍了对于配置VAI吊挂系统的250 t顶底复吹转炉采用倒装推移法进行主体设备整体安装的工程实践,并对其中拖动卷扬的能力选择、钢丝绳直径选择进行了计算,同时也提出了部分工序的主要安装技术参数。
This article introduced the project practice of the 250 tons BOF regarding disposes VAI to hang system which using inversion removing ways to carry on the main body equipment integral installing,and computed the choice of drag ability and steel wire diameter,and also proposed the primary installing technique parameter of the partial working procedures simultaneously.
出处
《冶金设备》
2010年第S1期113-115,121,共4页
Metallurgical Equipment
关键词
转炉
倒装
推移
奥钢联吊挂
Converter Reversed filling Removing VAI Con-link