期刊文献+

海底隧道CRD法各施工部开挖对结构内力影响

Study on influence of excavation by sections with CRD method on structural internal force in undersea tunnel
下载PDF
导出
摘要 以采用多部开挖矿山法施工的厦门东通道海底隧道为研究对象,选取四部开挖CRD法断面,研究CRD1、2部和CRD1、3部两种不同的开挖顺序对结构内力的影响。用振弦式钢筋计对隧道初期支护及临时支护的钢支撑进行应力监测,换算出钢支撑实际内力。对监测数据运用有限元方法进行数值建模计算,将监测数据分析结果与数值计算结果进行比较分析。研究表明:采用CRD1、2部超前开挖时的结构内力要略大于CRD1、3部超前开挖,CRD3部的开挖对结构内力的影响较大,两种开挖顺序的安全系数都满足规范要求,所以结构是安全的。 In terms of the technology of excavation by sections adopted in Xiamen East Passage Undersea Tunnel, a cross-section excavated by four sections with CRD method is selected to study the influence on the structural internal force when advanced excavation is conducted in CRD1&2 and CRD1&3 separately.In addition,stress monitoring has been conducted on the steel brace which is used as the initial support and the temporary support of the tunnel by vibrating-wire rebar gauges,and then the real internal force of the steel brace has been worked out as well.Meanwhile,the monitored data has been calculated by numerical modeling with finite element method. With the monitored results and the calculated results having been compared and analyzed,the research shows that the structural internal force is obviously larger when advanced excavation is conducted in CRD1&2 than in CRD 1 &3 and the excavation on CRD3 has a much greater influence on the structural internal force.The safety factors of both excavation methods can satisfy the needs of the specification,so the structure turns out to be safe.
出处 《辽宁工程技术大学学报(自然科学版)》 CAS 北大核心 2007年第S2期119-121,共3页 Journal of Liaoning Technical University (Natural Science)
基金 国家高技术研究发展专项(863计划)资助项目(2006AA11Z116)
关键词 海底隧道 CRD法 有限元方法 结构内力 安全系数 undersea tunnel CRD method finite element method structural internal force safety factor
  • 相关文献

参考文献3

二级参考文献13

  • 1黄伦海,刘伟,刘新荣.单洞四车道公路隧道开挖的模型试验[J].地下空间,2004,24(4):465-469. 被引量:26
  • 2贾明魁,赵兴东,贾安立.极软岩巷道底臌锚注支护控制技术[J].辽宁工程技术大学学报(自然科学版),2005,24(3):360-362. 被引量:18
  • 3刘招伟.某海底隧道暗挖施工关键技术及对策探讨[J].隧道建设,2005,25(5):1-3. 被引量:5
  • 4ESLAVA L F,MARULANDA A,RODRIGUEZ A J.Tunnelling in friable sandstone under high water pressure[A].Tunnels and Water[C].Rotterdam:Balkema,1989.1 325-1 332.
  • 5BACKER L,BLINDHEIM O T.The Oslofjord subsea road tunnel crossing of a weakness zone under high water pressure by freezing[A].Challenges for the 21st Century[C].Rotterdam:Balkema,1999.309-316.
  • 6FUKUCHI G.Seikan tunnel and water[A].Tunnels and Water[C].Rotterdam:Balkema,1989.1 189-1 194.
  • 7PALMSTROM A.Norwegian experience with subsea rock tunnels[A].Tunnels and Water[C].Rotterdam:Balkema,1989.927-934.
  • 8PALMSTROM A.The challenge of subsea tunnelling[J].Tunnelling and Underground Space Technology,1994,9(2):145-150.
  • 9重庆交通科研设计院.公路隧道施工技术规范(JTJ042-94)[S].北京:人民交通出版社.1995.
  • 10锚杆喷射混凝土支护技术规范(GB50086-2001)[S].北京:中国计划出版社,2001.

共引文献149

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部