铁城电站坝基岩体改良固结灌浆试验实践 被引量:2

MODIFIED CONSOLIDATION GROUTING TEST FOR DAM FOUNDATION ROCK OF TIECHENG HYDROPOWER STATION
原文传递
导出
摘要 针对铁城电站花岗片麻岩坝基岩体特点,选定5个特征试验区,梅花形布孔进行固结灌浆试验,进而布孔检验。通过波速测试、压水试验、岩芯等多种手段来对灌浆试验效果进行系统评估。数据结果分析表明,坝基岩体的可灌性较好,主体坝基固结灌浆设计方案可行。试验同时得出一些经验,并分析提出工程建议。 The dam foundation of Tiecheng hydropower station consists of granite-gneiss, where developed 2 faults, and 3 sets structural fractures. According to the site characteristics, 5 typical test divisions have been designed and consolidation grouting test carried out through 35 holes which were arranged as quincunx pattern. After 14 days from the day while grouting test completed, 3 examination holes have been designed for evaluating effectiveness of grouting test by means of wave velocity test, packer permeability test and rock core analysis.
作者 高德树
出处 《甘肃地质》 2009年第1期87-89,96,共4页 Gansu Geology
关键词 固结灌浆 波速 压水试验 耗灰量 consolidation grouting wave velocity packer permeability mortar consumption
  • 相关文献

参考文献2

  • 1DL/T5010-2005,水利水电工程物探规程[S].北京:中国电力出版社,2005(1).
  • 2DL/T5148-2001,水工建筑物水泥灌浆施工技术规范[S].北京:中国电力出版社,2002.

共引文献2

同被引文献4

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部