摘要
本文详述了东滩煤矿副井三维变形监测的方案设计及实施方法,列出了监测及分析结果,并对方法的可靠性及效应进行检验。
This paper describes the realization of the 3D deformation monitoring of Dongton coal mine's shaft. Some results of deformation monitoring and deformation analysis are presented. Its reliability and effect are verified.
出处
《地矿测绘》
1998年第4期3-6,共4页
Surveying and Mapping of Geology and Mineral Resources
基金
煤炭部出国留学人员基金
煤炭部1997年一般项目资助
关键词
井筒变形
三维变形监测
变形分析
Shaft's deformation
3D deformation monitoring
Deformation analysis