摘要
在援建孟加拉国公路大桥水下连续墙的成槽施工中采用自行研制的自动控制液压水下连续墙挖机,使成槽施工过程实现自动化,确保设计、施工要求,体现了该设备的可靠性和优越性。
In the construction of submarine consecutive wall for the China-aidded Bangladesh highway bridge, a selfmade automatic hydraulic digger for the construction of submarine consecutive wall sas adopted to automatized the construction work, and to guaranttee the required quality of construction, the reliability and advantages of this machine were fully demonstrated.
出处
《黑龙江大学工程学报》
1996年第1期61-63,70,共4页
Journal of Engineering of Heilongjiang University
关键词
成槽
预置
检测
trench digging
precasting
testing.